Summary
The Logistics Cluster convened humanitarian partners in Kismayo to review flood risks, access constraints, and El Niño preparedness across Jubaland. Partners were updated on ongoing cargo pre-positioning efforts, with over 560 MT of relief supplies delivered, while preparedness activities including boat deployment, fuel pre-positioning, and MSU allocation continue to advance. A key outcome of the meeting was the endorsement of SEDHURO as the Jubaland Logistics Cluster Partner Focal Point to support coordination and information sharing at the sub-national level.
Content
| LOCATION | Kismayo, Somalia Jubaland sub-national coordination meeting |
| DATE | 22 October 2026 |
| CHAIR | Logistics Cluster |
| PARTICIPANTS |
Agency for Relief and Development Organization (ARDO), Agency for Technical Cooperation and Development (ACTED), Area-Based Coordination (ABC), Catholic Relief Services (CRS), Horn Aid (HA), Human Appeal (HA), Juba Foundation (JF), Jubaland Youth Association (JYA), Livelihood Initiative for Disability Organization (LIDOSOM), Ministry of Heath in Jubaland (MHJ), Norwegian Church Aid (NCA), Rural Agency for Community Development and Assistance (RACIDA), Social-Life and Agricultural Development Organization (SADO), Vétérinaires Sans Frontières Suisse (VSF-Suisse), World Food Programme (WFP) and World Vision International (WVI)
|
| AGENDA |
|
| ACTION POINTS. |
|
- Flood Outlook and Risks
Partners were briefed on the flood outlook for 15–20 October 2026 (updated weekly based on FAO forecasts) and the potential humanitarian and logistics impacts.
- Moderate to heavy rain is forecast across central and southern Somalia, with very heavy rain expected in Hiraan, Galgaduud, Bay, Bakool, Gedo, Shabelle and Juba.
- Rain in the Ethiopian highlands may raise river flows. The Belet Weyne, Jowhar, Luuq and Dollow gauge stations are currently below flood thresholds; however, continued rain may raise levels and cause localized flooding in flood-prone areas.
- Acoording to FAO reports, 595 strategic water sources are at high or very high risk. Priority districts are Jowhar, Belet Weyne, Luuq, Afgooye and Balcad, plus the flood-prone Shabelle and Juba corridors.
- Roads, bridges and supply routes may be cut, limiting aid delivery and access to services. Some locations have already received moderate to heavy rain, causing flash floods.
Recommended preparedness actions
- Review flood contingency plans and critical access routes.
- Monitor river levels and road accessibility in high-risk districts and regularly consult Logistics Cluster information products for the latest updates.
- Verify pre-positioned relief stocks and alternative storage and transport options.
- Coordinate closely with government entities and humanitarian partners on preparedness and response.
- Physical Access Update.
Partners were briefed on access conditions across roads, bridges, airstrips and ports (LogIE snapshot). Dollow airstrip has reopened, while 6 road corridors and 9 bridges remain closed, concentrated in Lower Shabelle, Juba, Bay and Gedo.
Road Access (22 corridors)
| Status | Corridors |
| Open | Zeila–Boorama–Hargeisa–Berbera; Burco–Garoowe–Boosaaso; Garoowe–Gaalkacyo; Garacad–Gaalkacyo; Gaalkacyo–Dhuusamarreeb–Beledweyne; Galkayo–Maxaas–Beletweyne (clan conflict); Jowhar–Balcad–Mogadishu (fragmented) |
| Restricted / partial | Beledweyne–Jowhar; Afgooye–Mogadishu; Jowhar–Mogadishu; Luuq–Doolow–El Wak; Dollow–Luuq–Baidoa (commercial only); Dollow–Belet Hawa; Afmadow–Dhobley; Hargeisa–Odweyne–Burco; Hobyo / Xarardheere spur |
| Closed | Baidoa–Dinsor–Qoryoley–Mogadishu; Mogadishu–Merca–Kismayo (ports open); Kismayo–Afmadow–Dhobley; Baidoa–Wajid–Luuq; Kismayo–Bardheere–Baidoa (insecurity); Luuq–Garbaharey (insecurity) |
- Southwest routes into Baidoa, Wajid, Diinsor and Hudur have been reported passable since the lifting of the AS blockade (partner and truck association reporting). However, due to the ongoing political situation in the region, these routes remain unpredictable and partners are advised to re-confirm locally before planning movements.
Bridges (17 key crossings)
| Status | Crossings |
| Open | Beledweyne (Shabelle), Jowhar (Shabelle), Buloburto (good condition), Doolow (old, vulnerable), Luuq (El Niño damage, vulnerable) |
| Restricted | Afgooye cluster (multiple, damaged), Jalalaqsi (very weak) |
| Closed | Balcad (Shabelle), Jilib / Jamaame (2–3), Bu’aale, Baardheere (collapsed 2023), Buurdhuubo (collapsed 2023), Baidoa / Buurhakaba junction, Sabiid–Canoole |
Air Access
- Open: main airport hubs (Mogadishu, Hargeisa, Baidoa, Garoowe, Kismayo, Bosaaso, Galkayo) and 9 airstrips (Dollow, Luuq, Wajid, Feerfeer, Jalalaqsi, Afmadow, Dhobley, Jowhar and Badhaadhe airstrips).
- Closed: El Wak, Qansaxdhere, Dinsor and Burhakaba. Qansaxdhere, Dinsor and Burhakaba are inaccessible due to security linked to ongoing political dynamics.
- Most accessible airstrips are rain-sensitive and may become unusable at short notice. Dhobley, Afmadow, Jalalaqsi and Bula-burte lie in flood-prone zones.
Sea Transport and Border Crossings
- Five ports are open: Mogadishu, Berbera, Bosaso, Merca and Kismayo.
- All border crossings with Ethiopia and Kenya are open. The Kenya-side customs point requires prior approval from the Government of Kenya; partners are encouraged to coordinate shipments in advance to avoid delays.
Operational Implications
- The Shabelle corridor has the least redundancy. Flooding could cut the Dhusamareb and Beledweyne/Jowhar–Mogadishu supply lines, with few alternatives.
- Air back-up is not guaranteed, as most accessible airstrips are rain-sensitive and may close at short notice. Due to funding constraints, the Logistics Cluster will not have a helicopter this year (in 2023 it was funded by ECHO). Any UNHAS helicopter capacity would be limited to evacuation and movement of humanitarian staff and life saving cargo.
- Alternate routes exist: Berbera–Ethiopia into Bakool/Gedo is open, and Southwest routes are reported passable. The OCHA Access Working Group (AWG) is mapping alternative corridors for the UNSOS withdrawal and El Niño preparedness, in coordination with the Logistics Cluster and other partners. The Dhobley–Mandera border crossings remains a key alternative if other routes are cut off.
-
Partners were asked to report any change in road, bridge or airstrip status to the Logistics Cluster as it happens.
More details on the below link https://logie.logcluster.org/?op=som
- El Niño Preparedness and Anticipatory Actions.
Partners were briefed on the Logistics Cluster El Niño flood preparedness plan, which aims to enable rapid humanitarian access, cargo and fuel pre-positioning in flood-affected areas. The overall readiness target is 95%. The Logistics Cluster stressed that investing in preparedness and pre-positioning ahead of El Niño avoids costly last-minute logistics solutions later.
El Niño Flood Preparedness – Readiness Snapshot
| Readiness area | Status | Details |
| Boats pre-positioned | 70 boats, 60 deployed | 48 partner boats (maintained by the Logistics Cluster), 12 new inter-agency Logistics Cluster boats, 10 SoDMA boats being deployed |
| Boat maintenance and deployment | 39 fully maintained and ready, 13 new deployed | Ready for deployment. |
| Boat operators | 159 being trained (target 276) across jubaland and Hirshabelle state | Training by location (2 days each), started in Luuq and Jowhar in coordination with OCHA, SoDMA and MoHADMA |
| High and medium risk locations | 11 locations (6 high, 5 medium) | Beletweyne, Bulo Burto, Jalalaqsi, Jowhar, Balcad; Dollow, Luuq, Baardheere; Burdhuubo, Afmadow, Jamaame, Dhobley |
| Fuel reserve | 17,500 L pre-positioned | Initial stock across 11 strategic hubs, more can be deployed against verified need |
| Mobile Storage Units (MSUs) | 10 new MSUs available | For relocation of stocks to higher ground, allocated to a lead partner on condition the capacity is shared. The Logistics Cluster covers transport, installation and maintenance |
| Tabletop exercises (TTX) | 2 completed (100%) | Beletweyne, 7–9 Sept 2026 (35 participants); Kismayo, 5–7 Oct 2026 (37 participants), approx. 70 participants from 41 humanitarian organizations and 2 government entities |
Alignment
- Preparedness plans are aligned with the SoDMA roadmap (translated into logistics priorities), OCHA, ICCG partners and the HCT El Niño Preparedness Task Team.
- Logistics Cluster Operations & IM Updates.
Cargo Pre-positioning (as of 22 October 2026)
- As of 22 October 2026, the Logistics Cluster had received 69 service requests from 24 partner organizations, representing 633.11 MT and 1,454 m³ of humanitarian supplies (69 consignments) destined for 13 locations. Service requests have increased by 60.5% (from 43 to 69, after rising from 22 to 43 previously), a positive sign that partners are pre-positioning ahead of El Niño.
- To date, 560.36 MT (1,249.24 m³) across 60 consignments has been transported. 9 requests were in progress, totalling 72.75 MT (204.84 m³). Only 3 SRFs remain pending; these are difficult movements (e.g. Luuq to Baardheere, internal movements from Dollow) that depend on UNHAS flight availability.
- Priority delivery locations include Belet Weyne, Jowhar, Bulo Burte, Balcad, Luuq, Qansax Dheere, Kismayo, Afmadow, Dhobley, Baardheere, Buurdhuubo, Jalalaqsi, Garbaharey and Baidoa.
- The operational priority is to convert the transport pipeline into completed deliveries before access constraints intensify.
- The Logistics Cluster acknowledged ECHO for funding these preparedness and common services activities.
- Partners were reminded to submit storage and transport requests through the online Service Request Form (SRF) through the Logistics Cluster website at Rita - Relief Item Tracking Application.
Information Management: GNA, CONOPS and LCA
- Gaps and Needs Analysis (GNA): 26 partner organizations had responded to the survey. More are expected. Next, 10 humanitarian partners will be invited to one-to-one interviews to validate the feedback and follow up on key logistics gaps, improvements and recommendations. Finalization is expected end of early November 2026.
- Concept of Operations (CONOPS): will be revised based on the GNA findings and shared with humanitarian partners, donors and the Government.
- Logistics Capacity Assessment (LCA): under way in parallel, covering context analysis, logistics infrastructure, access, customs and tax exemption procedures, and entry points. About 50% of data collection is complete; the remainder is expected to be completed before the end of the year.
- Jubaland Partner Focal Point Nomination.
Partners were presented with the results of the consultation on the Jubaland Logistics Cluster partner focal point.
- 50 responses were received, with 100% support for a partner focal point. After removing 10 repeat submissions, responses represented approximately 40 organizations.
- SEDHURO received the support of 29 of 40 organizations (about 72%); 38 of the 50 raw submissions. World Vision received 2 votes, and ARDA, HDC, RACIDA, SEA, Alight and WFP received 1 vote each.
- Partners cited coordination, field presence and trust as the main reasons for their choice, with many referencing SEDHURO’s protection work. The top qualities sought were coordination (45), presence in Jubaland (36), representing all partners (28), communication (24) and logistics expertise (20).
Next steps
- Review and endorse the elected partner organization.
- The elected focal point will be the key Logistics Cluster focal point for coordination and information management in Jubaland and will co-chair sub-national coordination meetings with the Logistics Cluster.
- Outcome: No objections were raised, and partners endorsed SEDHURO as the Logistics Cluster partner focal point for Jubaland. The Logistics Cluster will coordinate with SEDHURO on the nomination of a logistics focal person.
- Partners were reminded that WFP has an office in Dollow, and the Logistics Officer in Dollow (Kassim Abdisheikh) is the first point of contact for any requests or issues in Jubaland.
- Partners Update.
- LIDOSOM (Gedo) shared an update on the ongoing rehabilitation of El Wak airstrip, carried out by the community and private sector with the local authority. About 1.5 km of runway is being filled and levelled, with plans to extend it to 2.5 km.
- Remaining gaps include limited passenger and cargo handling facilities, an inadequate passenger waiting shelter and the lack of operational office for airstrip staff.
- AoB
- No additional items were raised for discussion.
Upcoming meetings:
- Mogadishu national bi-weekly coordination meeting: 27 October 2026.
- Next Jubaland sub-national coordination meeting on 10 November 2026. The exact date and time will be confirmed by email.
- Beletweyne sub-national coordination meeting: 19 November 2026.
Contacts
|
Christian KACHIBI Hassanbulle NUNOW |
Logistics Cluster Coordinator Information Management Officer |