BRIDGE AND DECK ASSESSMENT KODDAIKKALAR NORTH OF KALLAR BETWEEN BATTICALOA AND KALMUNAI 27/03/05
See previous UNJLC eastern road assessment: Picture P1102,1103,1104,1105,1106
|
Date |
Waypoint |
Designation |
Grid Reference |
Causeway Location |
|
26/01/05 |
39.2 |
B6 |
N7°29.67’ E81°48.5’ |
North of Kallar |
More pictures available in the document attached below on the the website (click on the following picture)
Drainage has not been considered in the new causeway and deck construction. The bridge allows the passage of the vehicles one by one.
See previous UNJLC eastern road assessment: picture P1111
|
Date |
Waypoint |
Designation |
Grid Reference |
Causeway Location |
|
26/01/05 |
40.1 |
C5 |
N7°29.7’ E81°48.5’ |
North of Kallar |
More pictures available in the document attached below on the the website (click on the following picture)
Reinforced concrete side walls have been constructed to protect the deck. Drainage has not been considered in the new causeway and deck