Yei - Farasika Bridge Collapse: Update
Source UNJLC
Theme Overland Transport
Countries Sudan
Document type Other
Publication date 10/12/2007

UNJLC assessed the Yei-Farasika Bridge on a Juba-Yei-Farasika-Mundri road assessment between December 7th-9th.

The bridge has been temporarily repaired as seen in the attached photo. The bridge is open to 4WD vehicles and trucks. We recommend a maximum payload of 15 mertic tonnes for this bridge and all other bridges on the Yei-Farasika road.